Category ProjectsDredging
Dredging of the Hulhule-Hulhumale Link Road

The link road between Hulhule and Hulhumale required dredging along the existing alignment, together with removal of the dredged material. We completed the full scope in 75 days on a corridor that had to stay operational throughout.

ClientHunan No 6 Engineering Co., Ltd
LocationHulhule and Hulhumale, Maldives
Year2015
Duration75 days
Contract valueUSD 610,362

Scope of works

  • Dredging of the works area
  • Transport of dredged material
  • Completed in full

Planning a similar project?

Talk to our team about the site conditions, engineering requirements and delivery approach for your project.

Discuss a project
top