Category ProjectsMarine Infrastructure
Concrete Jetty and Quay Wall

Building a jetty on a small resort island means every stage has to be sequenced around limited working space. We carried out excavation, prepared the bund for piling, profiled the beach and removed construction waste by barge.

ClientYacht Tours Maldives Pvt Ltd
LocationKuda Rah, Maldives
Year2014
Duration5 months
Contract valueMVR 3.2 million

Scope of works

  • Excavation
  • Bund preparation for piling
  • Beach profiling
  • Construction waste disposal to barge

ServiceMarine Infrastructure

Planning a similar project?

Talk to our team about the site conditions, engineering requirements and delivery approach for your project.

Discuss a project